Bigfoot Project · Cutler Bay, Florida

Impact Window and Door Replacement in Cutler Bay

An impact window and door replacement project in Cutler Bay. Final inspection passed on August 28, 2026, under the Town of Cutler Bay building permit.

Project
Impact windows and doors
Municipality
Town of Cutler Bay
Final inspection passed
August 28, 2026

Project overview

This Bigfoot project involved impact window and door replacement in Cutler Bay. The Town of Cutler Bay building permit covered residential windows and doors.

Bigfoot Construction Inc pulled the Town of Cutler Bay building permit. The permit application was submitted on May 11, 2026, and the Town issued the permit on July 13, 2026.

The final inspection passed on August 28, 2026.

Permit timeline

  1. May 11, 2026 Permit application submitted to the Town of Cutler Bay.
  2. July 13, 2026 Permit issued by the Town of Cutler Bay.
  3. August 28, 2026 Final inspection passed.

From permit application (May 11, 2026) to passed final inspection (August 28, 2026): about 16 weeks. The Town of Cutler Bay issued the permit on July 13, 2026, and the final inspection passed about 7 weeks after it was issued.

Before, delivery and after

Planning your window and door project?

Explore impact window services in Cutler Bay or contact Bigfoot to discuss your project.