A shingle roof replacement featuring GAF Timberline HDZ in Charcoal, with fascia work and a wood-replacement change order. Explore the before views and installation work.
Location · Cutler Bay, FloridaShingles · GAF Timberline HDZColor · CharcoalDocumented stages · Before & in progress
The story behind the roof
The work starts below the surface.
The measurement report documents an existing asphalt shingle roof with six slopes, 2,024 square feet of roof area, and a 3/12 pitch. The sold replacement scope covers 22 roofing squares.
The sold scope includes full shingle replacement and 186 linear feet of new fascia. A wood-replacement change order added 30 linear feet of truss reinforcement and plywood decking work. Delivery records list eight sheets of 5/8-inch plywood and 29 fascia boards.
The before and progress photographs show the roof layout, removal work, exposed decking, and blue tarps around the home. Explore these stages with Billy and watch the project videos. Finished-roof photographs will be added when available.
BeforeExisting shingle roof
→
Documented workRemoval & preparation
In progress · The crew and protected work area.
Materials and project records
GAF shingles. Documented roof work.
Timberline HDZ in Charcoal
The supplier orders list GAF Timberline HDZ shingles in Charcoal, GAF Seal-A-Ridge ridge cap in Charcoal, and GAF Pro-Start starter shingles.
The original roof measurement is 2,024 square feet; the sold replacement scope is 22 roofing squares.
Leak barriers & ventilation
The orders list 12 rolls of GAF WeatherWatch and one StormGuard leak barrier, plus GAF Cobra Rigid Vent 3.
Additional ordered components include Karnak #155 sealant, Pure Flexiboot pipe flashings, 3 × 3 black drip edge, valley metal, angle flashing, a gooseneck, coil nails, and tin caps.
Fascia & wood work
The sold scope includes 186 linear feet of fascia. A sold change order covers 30 linear feet of truss reinforcement and plywood decking work.
Delivery records list eight sheets of 5/8-inch plywood and 29 fascia boards. These are delivered quantities, rather than a final installed-material count.
Permit & final inspection
Miami-Dade County issued re-roof permit 2026058376 on July 15, 2026. A permit revision was permitted on August 5, 2026.
The permitting team confirmed that the final roofing inspection passed on August 19, 2026.
The project is presented as Cutler Bay, Florida. Its permit identifies the property as unincorporated Miami-Dade County, and the county issued the roofing permit.
What roof did the home have before?
The measurement report describes an asphalt shingle roof with six slopes, 2,024 square feet of roof area, and a 3/12 pitch.
Which shingles were selected?
The supplier orders list GAF Timberline HDZ in Charcoal, with Charcoal Seal-A-Ridge ridge cap and Pro-Start starter shingles.
What additional work was included in the sold scope?
The sold scope includes fascia work, and a change order adds truss reinforcement and plywood decking work.
Did the final roofing inspection pass?
Yes. The permitting team confirmed that the final roofing inspection passed on August 19, 2026.
Are finished-roof photographs available?
This page currently documents the before and in-progress stages. Finished-roof photographs will be added when available.
What would your next roof look like?
Tell Bigfoot Windows and Roofing about your home and the roofing project you have in mind.
This site uses cookies and similar technologies for analytics, site functionality, and improving your experience. By continuing, you agree to our use of cookies. View our Privacy Policy.